Using the PERT estimate, calculate the estimated duration of an activity given:
Optimistic Estimate = 21 days
Pessimistic Estimate = 110 days
Most Likely Estimate = 55 days
a) 62.5 days
b) 74 days
c) 65 days
d) 68.5 days

Respuesta :

Otras preguntas

how many hours are in 5 years?
Cache memory levels are based on proximity to ________
Which describes the behavior of members of a herd leaving an area to find food
Geometry! Please help! What is the volume of this right cone? 27π cm³ 200π cm³ 213π cm³ 300π cm³
In 509 bce Rome monarchy ended and was replaced by what form of new government
Thomas has four children. two of these children are extremely sociable and attend every school event they can. the other two children do not care to attend ever
what does cmyk stand for?
write 3954 in expanded form using powers of 10
Which non-metal or metalloid is the most reactive? A. Iodine (I) B. Chlorine (Cl) C. Boron (B) D. Germanium (Ge)
The smaller rectangle was scaled by a factor of 2 to produce the larger figure. use the drop-down menus to show the missing dimensions of the scale figure