5 men can complete a job in 4 days. In how many days can 10 men working at 1/4 of the previous rate complete the job?​

Respuesta :

ashlllloop ashlllloop
  • 12-06-2021
the answer is 8 days
Answer Link

Otras preguntas

Write six hundred twelve thousand, three hundred in the place-value chart. Then write the number in expanded
Who could access portable portraits that changed who had access to the technology?
What is the image of (-3,6) when reflected in the x-axis? A. (6,-3) B. (-3, -6) C. (3,-6) D. (3, 6)
direct or indirect "Susan is a lovely ten-year-old girl from Hawaii."
mention the importance of education.​
define 1 second time​
What is the area of the rectangle ABCD? Help
Which ocean borders the western coast of South America
Give three equivalent rates that describe the top speed of a tuna. At top speeds, how much faster can a swordfish swim than a killer whale?Which animal swims a
Could someone help me with this too? Much appreciated! I am a bit stuck.