What does it mean when earned value is above planned value?​

Respuesta :

seannicolas seannicolas
  • 22-10-2021

Answer:

More work has been completed than planned, and the task or project is ahead of schedule.

Answer Link

Otras preguntas

Isabel wants to sign up with the online social network TeenBook, which she heard about from her friends at school. The TeenBook asked Isabel for some personal i
please help! Super simple! There are 15 girls and 10 boys in a 5th-grade class. What is the ratio of girls to boys? Write this as a simplified fraction.
A rectangle has a perimeter of 42 inches its width is 8 inches how much longer is the length than the width
what are the possible complications with preeclampsia?​
What is the solution to this system of equations
The concept of checks and balances was established by the authors of the Constitution (3 points) so that no single branch of the government would gain too much
What is the value of X rounded to the nearest 10th
Multiply. (−3x+4)(2x−1)
What is one way in which local governments are similar to federal governments?
∆ABC ~ ∆DEF. If ∠A=35° and ∠E=55°, what is the measure of ∠C?