If it takes 4 workers 21 hours to paint how many hours will it take 12 workers?

Respuesta :

m11233982
m11233982 m11233982
  • 12-09-2022

Answer:

63 hours

Step-by-step explanation:

4 workers = 21 hours

12 workers = g

[tex] \frac{21}{4} \times 12 \\ = 63hours[/tex]

Answer Link

Otras preguntas

how did the conflict over slavery impact a development of North Carolina in the United States in the years before the Civil War​
What is an advantage of a pre-wedding consultation with the bridal couple? You can earn more money since the couple pays for the consultation It helps the phot
the copernican model of the universe was supported by?
The magnetic field around a current carrying wire at a distance of 1cm is twice as strong as 2cm . How does the Ford strength at 0.5cm compare to the field stre
2. When you think of a typical hero, what comes to mind? What qualities does Phoenix (the main character in “A Worn Path”) share with the typical hero? What qua
Which number on the map represents the country of Iraq?
Plz Help! If 0.0025 mol NaNO3 forms during the reaction, what is the concentration of NaNO3 in the final solution? Please give a step-by-step solution to this p
Help with these sentences please
Which characteristic is expected of a mineral that crystallizes from lava at Earth’s surface
A dolphin swims 24 miles in 1.5