The most realistic estimate of the time required to complete an activity is referred to as​ what?
a. slack time
b. optimistic time
c. most likely time
d. pessimistic time

Respuesta :

sydneybottom
sydneybottom sydneybottom
  • 11-01-2018
I would say B. optimistic time
Answer Link

Otras preguntas

I need help on (a) I don't know what equation to use?
what is -2a(3-a) equivalent to
How to solve 5x+8y=14 And 4x=24 by substitution
How did the second continental congress respond to the eruption of fighting?
3x36÷(30÷5x2) Please solve using PEMDAS
How do you round a decimal to the nearest hundredth. Please use the problem below with steps on how to do the following action. 29/337 What I do is 29 divided
Which did the early river valley civilizations have in common? A. The nearby rivers were good for farming but made trade difficult. B. They built cities along r
What organization focuses on the maintenance of a peaceful alliance between North and South America?
why did scientists find it so hard to classify the platypus?
Fill in the blank. Cells, ______, Organs, Organs Systems.