sharixiii8804 sharixiii8804
  • 11-01-2018
  • Mathematics
contestada

If six men can do a piece of work in 14 days. how many are needed to complete the project in 21 days

Respuesta :

Davidfridman
Davidfridman Davidfridman
  • 12-01-2018
you would need 9 poeple
Answer Link

Otras preguntas

A simple random sample of 49 8th graders at a large suburban middle school indicated that 89% are involved in some type of after school activity. Find the 95% c
Find the perimeter of the composite figure
A pair of shoes usually sells for $63. If the shoes are 40% off, and a sales tax of 7% is applied to the discounted cost, what is the total price of the shoes,
Select all the decimals that round to 40 when they are rounded to the tens place.a) 42.59b) 37.155c) 45.78d) 45.167e) 34.989​
The function f is defined as follows. f(x) =5x² +8 If the graph off is translated vertically downward by 5 units, it becomes the graph of a function g. Find the
GIVING BRAINLIEST!!!!!!!!!!!!!!!!!!!
a rectangular shoebox has a volume of 160 cubic inches. the base of the shoebox measures 8 inches by 5 inches. how long is the shoebox?
Can yo solve this ones, please? in adittion, can you put answers and the process. The topic are area down the curve
help me with this pleaseeeeeee
Factor −4x^2 +6x. Is this a special product?